NEW QUESTION # 26
Under both FIDIC Yellow Book (YB) and Silver Book (SB) (edition 1999), if the Engineer (YB) / Employer (SB) instructs the Contractor based on Sub-Clause 8.6 to provide a revised programme, the acceptance by the Engineer (YB) / Employer (SB) of a revised programme with a completion within Time of Completion entitles the Contractor to a payment of the needed extra costs. Is this statement true or false?
- A. True
- B. False
Answer: B
Explanation:
This statement is false. Acceptance of a revised programme that shows completion within the Time for Completion does not automatically entitle the Contractor to extra payment. The Contractor must demonstrate additional costs arising from the instruction or circumstances to claim payment.
The acceptance of a compliant programme is a scheduling and administrative matter, not a compensation guarantee.
References:
FIDIC Yellow and Silver Books 1999 Editions, Sub-Clause 8.6 - Revised Programme FIDIC Contract Manager Study Guide, Module on Claims and Payment
NEW QUESTION # 27
Regarding the FIDIC Red Book (edition 1999), which two statements are true?
- A. A notice is to be signed by the Engineer, Contractor's Representative or Employer's Authorised Representative.
- B. A notice and other communications may be delivered by hand, courier and mail. In each case with proof of receipt is required to qualify as legally valid.
- C. In emergency situations notices can also be submitted verbally (rather than (also) in writing).
- D. Notices and other communications may be sent in hand written, type written, in print or through an electronic original transmission system.
Answer: C,D
Explanation:
Comprehensive and Detailed Explanation:
Option A is true: In emergencies, verbal notices are permitted with the requirement to follow up in writing.
Option D is true: Notices and communications may be sent in various formats including handwritten, typed, printed, or electronic systems.
Option B is incorrect; a notice does not necessarily have to be signed by all these representatives; it depends on the party issuing the notice.
Option C is incorrect; proof of receipt is ideal but not always strictly required for legal validity depending on contract provisions.
References:
FIDIC Red Book 1999 Edition, Sub-Clause 1.3 - Communications and Notices FIDIC Contract Manager Study Guide, Module on Contract Communication
NEW QUESTION # 28
Which two of the following statements are correct, regarding the Programme under FIDIC Red, Yellow and Silver Books (edition 2017)?
Choose all of the correct answers (multiple possibilities).
- A. Nothing in any Programme will relieve the Contractor from any obligations to give contractual notice under the Conditions of Contract.
- B. The Programme is a contract document, and thus, considered binding on the Parties.
- C. The Contractor is required to proceed in accordance with the Programme and the Employer's Personnel shall be entitled to rely upon the Programme in planning their activities.
- D. The Engineer/Employer is not required to review the Programme, and also not required to inform the Contractor if the Programme does not comply with the Contract.
Answer: A,C
Explanation:
Comprehensive and Detailed Explanation:
Option A is correct: The Contractor must proceed according to the approved Programme, and the Employer's personnel rely on the Programme for coordinating their activities.
Option B is correct: Submission and approval of the Programme do not relieve the Contractor of the obligation to give timely notices for delays or other events as required under the contract (e.g., notices under Sub-Clause 8.4).
Option C is incorrect because the Programme is not strictly a contract document binding parties in the legal sense; it is a working tool to manage and monitor progress.
Option D is incorrect; the Engineer/Employer must review the Programme and notify the Contractor if it does not comply, per contract clauses.
References:
FIDIC Red, Yellow, and Silver Books 2017, Sub-Clause 8.3 and 8.4 - Programme and Notices FIDIC Contract Manager Study Guide, Module on Time and Delay Management
NEW QUESTION # 29
Under the FIDIC Construction Contract, which one of the following statements is correct?
- A. Payments of a DAB Member's retainer fee is the sole responsibility of the Contractor.
- B. If all persons nominated to serve as members of an ad hoc DAB do not sign a DAB Agreement, an appointing entity can make appointments.
- C. A DAB must give its decision in writing on any dispute when requested by one of the Parties.
- D. Payment to DAB Members must be certified by the Employer.
- E. For an ad-hoc DAB, a retainer fee for each DAB Member must be paid to the Member on the first day of each calendar month.
Answer: C
Explanation:
Under the FIDIC Conditions of Contract (particularly 2017 editions), the Dispute Adjudication Board (DAB) is a standing or ad hoc body that provides binding decisions on disputes. One key requirement is that the DAB must give its decisions in writing upon request by either Party, ensuring clarity and enforceability.
Option E is correct as the DAB's decision must be documented formally.
Option A is incorrect; the cost of the DAB is generally shared by Employer and Contractor as per the contract.
Option B is incorrect because retainer fees can be paid on different schedules, not necessarily monthly on the first day.
Option C is incorrect; payments to DAB members do not require Employer's certification but are agreed as part of the DAB contract.
Option D is partially true but not a standalone correct statement without additional context.
References:
FIDIC Red, Yellow, Silver Books 2017 Edition, Clause 21 - Disputes and DAB Procedures FIDIC Contract Manager Study Guide, Module on Claims and Dispute Resolution
NEW QUESTION # 30
When is the Employer obliged to return the Performance Security (PS) under the FIDIC Red Book (edition
1999)?
- A. Within 21 days after the issuance of the Performance Certificate.
- B. Within 21 days after the issuance of the Taking-Over Certificate.
- C. Without undue delay after the issuance of the Performance Certificate.
- D. Without undue delay after the issuance of the Taking-Over Certificate.
Answer: A
Explanation:
Comprehensive and Detailed Explanation:
Under FIDIC Red Book 1999, the Performance Security (or Performance Guarantee) is held to ensure the Contractor's performance during the defects liability period. The security is typically released only after the Employer issues the Performance Certificate, which confirms the completion of defects liability obligations and that the Contractor has fulfilled the contract.
The contract commonly specifies a fixed period (often 21 days) within which the Employer must return the Performance Security after issuance of the Performance Certificate (Option D). The Taking-Over Certificate (Options A and C) marks substantial completion but does not end the Contractor's obligations for defects.
References:
FIDIC Red Book 1999, Sub-Clause 10.2 - Taking-Over Certificate
FIDIC Red Book 1999, Sub-Clause 10.4 - Performance Certificate
FIDIC Red Book 1999, Sub-Clause 10.5 - Release of Performance Security
FIDIC Contract Manager Study Guide, Module on Payment Procedures and Financial Management
NEW QUESTION # 31
You are the Contract Manager for the Engineer in a hospital project using FIDIC Yellow Book (edition 2017).
The Employer demands perfection in the project's design and construction quality. There are many Variations initiated by the Employer during design and construction. Which one of the following is considered to be a valid Variation?
- A. The Contractor submits a Value Engineering proposal regarding the lighting system for the operation rooms. The Engineer is positive about the proposal and tells the Contractor they need to look into it.
- B. The Engineer instructs a change in slopes of the access road to the intensive care unit to meet the Employer's Requirement. The Engineer does so with a Notice in accordance with Sub-Clause 3.5.
- C. The Engineer requests a proposal regarding a change in type of windows and doors. The Contractor submitted the proposal accordingly to the Engineer. The Engineer instructs the Variation.
- D. The Employer verbally instructs a change in the type of doors. The Engineer issued a Notice describing the required change and denying any costs for the Contractor.
Answer: B
Explanation:
Comprehensive and Detailed Explanation:
Option B is correct: A Variation is a formal change to the Works instructed by the Engineer via a Notice (Sub- Clause 3.5). This includes changes to design or execution such as slopes on a road.
Option A is a proposal, not yet a Variation. Positive interest does not constitute a Variation.
Option C is partially correct but depends on formal instruction after proposal acceptance; the question specifies the Engineer instructs the Variation, but since it was a request for proposal first, the Variation instruction comes later. Without explicit instruction, this is not yet a Variation.
Option D is invalid as verbal instruction plus a Notice denying cost claims does not constitute a proper Variation.
References:
FIDIC Yellow Book 2017 Edition, Sub-Clause 3.5 - Variation Procedure
FIDIC Contract Manager Study Guide, Module on Variations and Change Management
NEW QUESTION # 32
Under the FIDIC Yellow Book (both editions), the Contract is administered by the Employer (unless it appoints an Employer's Representative) who endeavours to reach agreement with the Contractor on each claim. Is this statement true or false?
- A. False
- B. True
Answer: B
Explanation:
Comprehensive and Detailed Explanation:
This statement is true. The Employer administers the contract unless an Employer's Representative or Engineer is appointed to act on its behalf. The Employer (or its Representative) is responsible for reviewing and negotiating claims in good faith with the Contractor to reach agreement, in line with FIDIC procedures.
References:
FIDIC Yellow Book 1999 & 2017 Editions, Clause 3 - Employer's Administration Role FIDIC Contract Manager Study Guide, Module on Contract Administration
NEW QUESTION # 33
Which two of the following statements are correct regarding the dayworks under FIDIC Red, Yellow, and Silver Books (both editions)?
Choose all of the correct answers (multiple possibilities).
- A. If a Daywork Schedule is not included in the Contract, the Sub-Clause related to dayworks shall not apply.
- B. The dayworks related Sub-Clause is only used for remeasurement in the FIDIC Red Book (both editions) only.
- C. The dayworks related Sub-Clause is also applicable to other types of works.
- D. The Engineer (or the Employer in case of FIDIC Silver Book) may instruct that "a Variation shall" be executed on a daywork basis.
Answer: C,D
Explanation:
Dayworksrefer to works executed on a time basis (e.g., labor and plant) with payment made according to predetermined rates rather than a lump sum or unit rate contract price.
* Option Aisincorrect. Even if a Daywork Schedule is not initially included, the dayworks Sub-Clause (e.g., Sub-Clause 13.7 in Red and Yellow Books, 13.8 in Silver Book 1999) still applies to dayworks ordered during the contract execution. The schedule facilitates pricing, but the Sub-Clause governs the method and conditions for dayworks.
* Option Biscorrect. The dayworks Sub-Clause is applicable not only to traditional construction works but can also be applied to other types of works, such as variations or additional works that cannot be precisely measured or foreseen and are charged on a time basis.
* Option Cisincorrect. The dayworks Sub-Clause is used in all FIDIC standard forms (Red, Yellow, and Silver Books), not only for remeasurement in the Red Book. In the Yellow Book (plant and design- build) and Silver Book (EPC/turnkey), dayworks are similarly applicable for certain variations or unforeseen works.
* Option Discorrect. The Engineer (in Red and Yellow Books) or the Employer (in the Silver Book, where the Engineer's role is limited) may instruct that a variation be executed on a daywork basis. This instruction is typically used when the scope or quantity cannot be reasonably pre-determined.
References:
FIDIC Red Book 2017 Edition, Sub-Clause 13.7 - Dayworks
FIDIC Yellow Book 2017 Edition, Sub-Clause 13.7 - Dayworks
FIDIC Silver Book 1999 Edition, Sub-Clause 13.8 - Dayworks
FIDIC Contract Manager Study Guide, Module on Contract Administration Procedures
NEW QUESTION # 34
Under the FIDIC Red and Yellow Books (edition 2017), which two of the following elements shall form part of the initial time Programme?
- A. The sequence and timing of the remedial work.
- B. The date on which the right of access to and possession of (each part of) the Site is to be given to the Contractor.
- C. The actual progress to date, any delay to such progress and the effects of such delay on other activities (if any).
- D. All key delivery dates of Plant and Materials.
Answer: B,D
Explanation:
Comprehensive and Detailed Explanation:
Option A is correct: The initial programme must include the date for the Contractor's access to the Site.
Option D is correct: Key delivery dates for Plant and Materials are essential elements of the programme.
Option B relates to updated/revised programmes, not the initial programme.
Option C generally relates to remedial work and is part of revised or detailed programmes.
References:
FIDIC Red and Yellow Books 2017 Edition, Sub-Clause 8.3 - Programme
FIDIC Contract Manager Study Guide, Module on Time and Delay Management
NEW QUESTION # 35
Both FIDIC Silver Book (SB) and Yellow Book (YB) (edition 1999) mention the Contractor scrutinising the Employer's Requirements. Which statement is correct?
- A. Scrutinising in FIDIC Yellow Book 1999 and Silver Book 1999 means that the Contractor must ask the Employer to check the Employer's Requirements very well to see if the Works can be built on that location according to the Employer's Requirements.
- B. Scrutinising in FIDIC Yellow Book 1999 means that the Contractor has the opportunity after contract close to report on any errors, mistakes or conflicts in the Employer's Requirements. In the FIDIC Silver Book 1999 scrutinising provides that obligation during the tender period; Contractor has the opportunity to report on any errors, mistakes or conflicts in the Employer's Requirements and for Employer to change it; for after contract closes this is not a duty anymore of Employer.
- C. Scrutinising in FIDIC Yellow Book 1999 means the same as in FIDIC Silver Book 1999. In both models it means that after the contract closes and before starting the actual making of the design, the Contractor has to read the Employer's Requirements very thoroughly and check on any errors, omissions or conflicts.
- D. Scrutinising in FIDIC Silver Book 1999 means that the Contractor should read the Employer's Requirements very thoroughly after the contract closes and see if the Employer's Requirements is complete or if something is missing.
Answer: B
Explanation:
mprehensive and Detailed Explanation:
Option D correctly captures the difference between Yellow and Silver Books (1999):
In the Yellow Book, the Contractor may raise concerns after contract close.
In the Silver Book, the Contractor must scrutinize and report on Employer's Requirements during the tender period, and after contract close this duty lapses.
Other options misunderstand timing or scope of scrutiny.
References:
FIDIC Yellow and Silver Books 1999 Editions, Sub-Clause 4.1 - Contractor's General Obligations FIDIC Contract Manager Study Guide, Module on Employer's Requirements and Scrutiny
NEW QUESTION # 36
The Employer has prepared a contract for a waste-to-energy project based on the FIDIC Yellow Book (edition
1999). You are preparing negotiations on behalf of one of the Subcontractors with the Contractor. The main Contractor will manage the design and build of the Works, whereby the Subcontractor will deliver critical systems regarding power generation and cooling. The Contractor intends to contract the main Contract back- to-back with the Subcontractor. In the proposed back-to-back subcontract, the following amendment is proposed through Particular Conditions:
"Sub-Clause 4.4. The following paragraph is added: The Subcontractor is required to scrutinize the Employer's Requirements in a manner identical to the obligations of the Contractor as stated in Sub-Clause
5.1 of the Main Contract. The Subcontractor will indemnify and hold harmless (up to the maximum liability of the Subcontractor) the Contractor with regard to any error, fault or other defect found in the Employer's Requirements, its items of reference or Contractor's design of the Works for the scope part for which Subcontractor is contracted." What is your advice to the Subcontractor (SC) in regard to entering this proposed subcontract?
- A. I would advise the SC not to enter this contract because the Contractor is obliged to act in accordance with good faith. A proposed paragraph like this opposes good faith.
- B. I would advise the SC not to enter this contract, because Sub-Clause 4.4 describes the obligations of SC towards Contractor, but this amendment positions the SC in a vulnerable position for claims regarding all errors, faults or other Defects (whether originating from the Employer's Requirements or the design of the Contractor). Essentially, this means the SC becomes liable for the design part, which is within the scope of Contractor even without SC having the opportunity to review it.
- C. I would advise the SC to discuss this amendment with the insurance company just to be sure there will be no transfer of risks. This amendment is mainly a consequence of the FIDIC Yellow Book structure, where the Contractor has obligations in terms of scrutinizing the Employer's Requirements. This amendment makes this obligation more explicit. If the insurance company has no problems with insuring the parts which will be delivered by SC to Contractor, the SC can accept this risk and enter into the subcontract.
- D. I would advise the SC to enter the Contract with the request to the Contractor to delete this amendment in the Particular Conditions. If the Contractor does not agree to do so, at least the Subcontractor has tried its best.
Answer: B
Explanation:
In FIDIC Yellow Book (1999), the Contractor is responsible for scrutinizing the Employer's Requirements per Sub-Clause 5.1 and must notify any discrepancies or errors. However, passing this obligation to a Subcontractor, and requiring the Subcontractor to indemnify the Contractor for errors or defects arising from the Employer's Requirements or the Contractor's design, unfairly shifts risk and liability to the Subcontractor.
The Subcontractor is likely not in a position to fully review or control the Employer's Requirements or the overall Contractor's design. This exposes the Subcontractor to excessive risk, beyond their scope and capacity.
Advice C highlights that the Subcontractor becomes vulnerable to claims for design defects outside their control. This misallocation of risk is generally not recommended and can be challenged during contract negotiation. Good contract management practice and risk allocation principles (FIDIC Contract Manager Study Guide, Module on Claims and Dispute Resolution) support this position.
While Options A, B, and D propose different approaches, only C correctly identifies the fundamental contractual and risk management issue that should prevent the Subcontractor from entering the contract as is.
References:
FIDIC Yellow Book 1999, Sub-Clause 5.1 - Contractor's General Obligations FIDIC Contract Manager Study Guide, Module on Claims and Dispute Resolution FIDIC Contract Manager Study Guide, Module on Risk Management
NEW QUESTION # 37
Under the FIDIC Red and Yellow Books (edition 1999), which two of the following statements are correct regarding the issuance of Interim Payment by the Engineer?
(Choose all correct answers - multiple possibilities)
- A. The Employer is bound by the Certificate issued by the Engineer and must make payment in full, irrespective of any entitlement to compensation arising from any claim which the Employer may have against the Contractor.
- B. If the Employer considers itself entitled to claim against the Contractor, notice and particulars must first be submitted under Sub-Clause 2.5. The Employer's entitlement is then to be agreed or determined by the Engineer, and then, incorporated as a deduction in a Payment Certificate.
- C. The Employer is bound by the Certificate issued by the Engineer, and must make payment in full, except for any compensation arising from any claim which the Employer may have against the Contractor.
- D. The Employer is not bound by the Certificate issued by the Engineer.
Answer: B,C
Explanation:
Under the FIDIC Red Book and Yellow Book, 1999 editions, the Engineer issues Interim Payment Certificates certifying the amounts due to the Contractor for completed works and materials on site (Sub- Clause 14.6). The Employer is generally bound by the Payment Certificate and must pay accordingly, except where there is a lawful set-off or compensation claim against the Contractor.
Option A is correct because the Employer must pay the amount certified except for compensation claims that may be offset against the payment (Sub-Clause 14.6).
Option D is also correct: If the Employer intends to claim against the Contractor (e.g., for damages or defects), it must notify the Contractor under Sub-Clause 2.5 and provide particulars. The Engineer then assesses and decides on the claim and incorporates any agreed deductions into the Payment Certificate.
Option B is incorrect because the Employer is indeed bound by the Payment Certificate unless lawful deductions or disputes arise.
Option C is incorrect as the Employer can withhold amounts due for compensation claims once these are properly notified and substantiated.
References:
FIDIC Red and Yellow Books, 1999 Edition, Sub-Clause 14.6 - Interim Payments FIDIC Red and Yellow Books, 1999 Edition, Sub-Clause 2.5 - Employer's Claims FIDIC Contract Manager Study Guide, Module on Payment Procedures and Financial Management
NEW QUESTION # 38
A large sewage pump installation has been constructed under the FIDIC Yellow Book (edition 1999). Prior to commencement of the Tests on Completion, the Employer requires the Contractor to issue the Operation and Maintained Manuals. All contract documents are to be drafted in the English language as per Sub-Clause 1.4.
However, the Employer discovers all documents are drafted in a different language: French. The Contractor explains that the territory where the Plant was constructed is a region with French as a second official language, as result of which, this approach is acceptable. This also works for the proposed maintenance company, which is Paris-based. The Employer is surprised and asks you what to do. Select the best fitting advice you should give the Employer.
- A. Golden Principle no. 1 states: The duties, rights, obligations, roles and responsibilities of all the Contract Participants must be generally as implied in the General Conditions, and appropriate to the requirements of the project. In this case this means it is appropriate that the Operation and Maintenance Manuals are in French, as the maintenance is based in France.
- B. The Employer should check on the Appendix to Tender, Employer's Requirements and / or Particular Conditions. There could very well be specific requirements regarding the language in those. If that is not the case, the language of the Contract determined in Sub-Clause 1.4 and the language of the Operation and Maintained Manuals should in this case be English.
- C. If French is indeed an official second language of the region where the Plant is built, the Contractor is entitled to deliver the documents in French. The usability in terms of language is not described in Sub- Clause 5.7, so the Employer should accept the Operation and Mantained Manuals in French.
- D. As the Contract is written in the English language, Sub-Clause 1.4 dictates that the Operation and Maintenance Manuals should be written in English as well.
Answer: B
Explanation:
The best advice is to verify specific contractual documents such as the Appendix to Tender, Employer's Requirements, and Particular Conditions, which may specify the required language for Operation and Maintenance Manuals. If no specific provision is made, the default language is that of the Contract as per Sub- Clause 1.4, which in this case is English.
Therefore, the Contractor is generally obliged to provide manuals in English unless otherwise specified.
Options B, C, and D are less comprehensive or may disregard contractual hierarchy or project-specific details.
References:
FIDIC Yellow Book 1999 Edition, Sub-Clause 1.4 - Language
FIDIC Yellow Book 1999 Edition, Sub-Clause 5.7 - Operation and Maintenance Manuals FIDIC Contract Manager Study Guide, Module on Contract Language and Documentation
NEW QUESTION # 39
A Contractor under the FIDIC Silver Book (edition 1999) has not been able to finish the Works within the Time for Completion as mentioned in the Contract and has overrun the Time for Completion by 3 months.
This results in a significant claim of $4,500,000 from the Employer. The Employer has submitted this claim to the Contractor according to the procedures as mentioned in the Contract. The Contractor asks you for advice and refers to Clause 8. Which one of the following statements is NOT true?
- A. If the delay is entirely caused by the Employer having instructed the Contractor to suspend progress during the Works, while the cause of the suspension is not the responsibility of the Contractor, the claim for delay damages was wrongfully issued.
- B. If there are Variations agreed between the Contractor and the Employer, the Contractor should check if an adjustment for Time for Completion was part of any of these Variations.
- C. The root cause of the delay has to be determined by the Contractor, thereby especially verifying if the cause of the delay lies in a delay caused by the Authorities.
- D. In addition to the delay damages as mentioned in Sub-Clause 2.5, the Employer has the right to claim any extra costs it has to make due to the delay, as delay damages are not seen as compensation for costs incurred by the Employer, but only as an incentive for the Contractor to perform on time.
Answer: D
Explanation:
Comprehensive and Detailed Explanation:
Option C is not true because under the FIDIC Silver Book (1999 edition), the delay damages (liquidated damages) specified in the contract are intended as full compensation for the Employer's loss resulting from late completion. The contract usually excludes other claims for actual losses or extra costs beyond the delay damages.
Option A is true; Variations can include extensions of time.
Option B is true; identifying delay causes is essential for claims and defences.
Option D is true; if the Employer causes suspension not attributable to the Contractor, delay damages claims by the Employer are generally unjustified.
Thus, the Employer cannot claim extra costs over and above delay damages as per typical Silver Book provisions.
References:
FIDIC Silver Book 1999 Edition, Sub-Clause 8 - Time for Completion and Delay Damages FIDIC Silver Book 1999 Edition, Sub-Clause 2.5 - Employer's Claims FIDIC Contract Manager Study Guide, Module on Claims and Delay Damages
NEW QUESTION # 40
Under the FIDIC Construction Contract, which one of the following statements is correct?
- A. Payments of a DAB Member's retainer fee is the sole responsibility of the Contractor.
- B. If all persons nominated to serve as members of an ad hoc DAB do not sign a DAB Agreement, an appointing entity can make appointments.
- C. A DAB must give its decision in writing on any dispute when requested by one of the Parties.
- D. Payment to DAB Members must be certified by the Employer.
- E. For an ad-hoc DAB, a retainer fee for each DAB Member must be paid to the Member on the first day of each calendar month.
Answer: C
Explanation:
Under the FIDIC Conditions of Contract (particularly 2017 editions), the Dispute Adjudication Board (DAB) is a standing or ad hoc body that provides binding decisions on disputes. One key requirement is that the DAB must give its decisions in writing upon request by either Party, ensuring clarity and enforceability.
Option E is correct as the DAB's decision must be documented formally.
Option A is incorrect; the cost of the DAB is generally shared by Employer and Contractor as per the contract.
Option B is incorrect because retainer fees can be paid on different schedules, not necessarily monthly on the first day.
Option C is incorrect; payments to DAB members do not require Employer's certification but are agreed as part of the DAB contract.
Option D is partially true but not a standalone correct statement without additional context.
References:
FIDIC Red, Yellow, Silver Books 2017 Edition, Clause 21 - Disputes and DAB Procedures FIDIC Contract Manager Study Guide, Module on Claims and Dispute Resolution